It is known that this is a project to implement the investment program of Grid-connected photovoltaic power system installed on the roof of raw material warehouse with a capacity of 1000kWp at C.P Vietnam factory in An Hiep industrial park, Ben Tre province.
As one of Hao Phuong’s long-term projects with high investment costs. Once completed, the company will sell electricity to customers every month, serving the need of supplying electricity to five areas in the aquatic feed manufacturing complex at the factory.
Project scale
Power quality
Guaranteed voltage and frequency as prescribed in Clause 1, Article 15 of Decree No. 137/2013 / Government Decree:
About the voltage
Under normal conditions, the permissible voltage deviation is within ± 5% of the nominal voltage of the grid and is determined at the location of the electricity meter or at another position agreed upon by the two parties. For the unstable grid after incident, the permissible voltage deviation is from + 5% to -10%;
About the frequency
Under normal conditions, the permitted deviation of the electrical system frequency within ± 0.2 Hz from the nominal frequency is 50Hz. For an unstable grid after a single incident, the permitted frequency deviation is ± 0.5Hz.
Electricity metering equipment conforms to Vietnam’s standards or equivalent international standards and is tested according to the provisions of Vietnamese law.
Construction items of the project
- Executing and installing RAIL and PIN
- Construction and installation of cable troughs.
- Construction of wire pulling and connecting
- Construction sanitary water pipe for PIN
Project progress
The project was started to install from the middle of March 2020, until now Hao Phuong has completed 9 systems on 12 solar battery power systems. It is expected that by the 3rd week of April 2020, 12 battery systems will be completed and energized.
Some photos of the project implementation process:
Install scaffolding on roofs
Processing fence support
Processing trough support
Rail transport and installation
Installation of Solar panels
Installing an electrical cable trough
Complete installation of 9-12 battery
Installing 1-8 battery rail system
Installing trough battery 9/12 system 100% complete
Install battery for 1-8 system
Install battery for 1-8 battery system
Move AC and DC box into installation location
Install the complete INV cabinet in the right position